1620 Fifth Avenue, Suite 770, San Diego, CA 92101.

logologologo
  • Home
  • Practice Areas
    • Real Estate Development & Construction
      • Litigation
      • Zoning Approvals And Permits
      • Development Agreements
      • Joint Venture Agreements
      • Finance Agreements
      • Construction Agreements
      • Real Estate Disputes
      • Risk Management
    • Construction Litigation
      • Construction Litigation
      • Custom Homes
      • Spec Homes
      • Remodels
      • Flips
      • Apartment Buildings
      • Commercial Buildings
      • Mixed Use Buildings (Housing + Commercial)
    • Commercial Real Estate
      • Land Use
      • Disputes Between Buyers and Sellers
      • Real Estate Law
    • Who We Represent
      • Builders
      • Contractors
      • Architects
      • Engineers
  • About
    • Dennis Stryker
    • Monica Slev
  • Insights
  • Case Results
  • Contact Us
  • Make A Payment

(866) 531-5705

logologologo
  • Home
  • Practice Areas
    • Real Estate Development & Construction
      • Litigation
      • Zoning Approvals And Permits
      • Development Agreements
      • Joint Venture Agreements
      • Finance Agreements
      • Construction Agreements
      • Real Estate Disputes
      • Risk Management
    • Construction Litigation
      • Construction Litigation
      • Custom Homes
      • Spec Homes
      • Remodels
      • Flips
      • Apartment Buildings
      • Commercial Buildings
      • Mixed Use Buildings (Housing + Commercial)
    • Commercial Real Estate
      • Land Use
      • Disputes Between Buyers and Sellers
      • Real Estate Law
    • Who We Represent
      • Builders
      • Contractors
      • Architects
      • Engineers
  • About
    • Dennis Stryker
    • Monica Slev
  • Insights
  • Case Results
  • Contact Us
  • Make A Payment

(866) 531-5705

  • Home
  • Practice Areas
    • Real Estate Development & Construction
      • Litigation
      • Zoning Approvals And Permits
      • Development Agreements
      • Joint Venture Agreements
      • Finance Agreements
      • Construction Agreements
      • Real Estate Disputes
      • Risk Management
    • Construction Litigation
      • Construction Litigation
      • Custom Homes
      • Spec Homes
      • Remodels
      • Flips
      • Apartment Buildings
      • Commercial Buildings
      • Mixed Use Buildings (Housing + Commercial)
    • Commercial Real Estate
      • Land Use
      • Disputes Between Buyers and Sellers
      • Real Estate Law
    • Who We Represent
      • Builders
      • Contractors
      • Architects
      • Engineers
  • About
    • Dennis Stryker
    • Monica Slev
  • Insights
  • Case Results
  • Contact Us
  • Make A Payment
by Admin
Construction LawNovember 19, 20260 comments

Understanding Retainage in Los Angeles Construction Contracts

Last updated: November 2026

Retainage is the share of each progress payment that an owner holds back from a contractor, or a contractor withholds from a subcontractor, until the project is finished. In California construction, Civil Code section 8811 caps retention at 5 percent on most private contracts signed on or after January 1, 2026, and sections 8812 and 8814 set release deadlines.

This guide is for owners, developers, general contractors and subcontractors working on Los Angeles and Southern California projects. Retention is governed by statewide California law. A project in Los Angeles follows the same statutes as one in San Diego, and the statutes call it “retention” rather than “retainage.”

What does California’s 5% retention cap change in 2026?

California’s 5 percent retention cap is Civil Code section 8811, added by Senate Bill 61 (Statutes of 2025, chapter 49, approved July 14, 2025). It limits retention on a private work of improvement, and it applies only to contracts entered into on or after January 1, 2026.

The cap works at every tier of the payment chain. Under section 8811, retention withheld from any payment cannot exceed 5 percent of that payment. That covers an owner paying a direct contractor, a direct contractor paying a subcontractor, and a subcontractor paying a lower-tier subcontractor.

There is also a ceiling on the total. Retention withheld over the life of the contract cannot exceed 5 percent of the contract price.

A subcontract cannot use a higher retention percentage than the owner’s contract with the direct contractor. So if the prime contract holds 3 percent, the subcontract cannot hold 5.

Two exceptions matter in practice. The cap does not apply when the contractor gave written notice, at or before the time bids were requested, that a performance and payment bond would be required, and the subcontractor then fails to furnish one from an admitted surety. It also does not apply to residential projects that are not mixed-use and are no more than four stories.

Section 8811 also gives the prevailing party in an enforcement action its reasonable attorney’s fees. If your company still signs from a subcontract form drafted before 2026, check the retention clause against section 8811 before the next project starts.

When must retention be released on a California project?

On a private project, California Civil Code section 8812 requires the owner to pay retention to the direct contractor within 45 days after completion of the work of improvement. Civil Code section 8814 then gives the direct contractor 10 days after receiving all or part of a retention payment to pay each subcontractor its share.

“Completion” has a specific meaning. Under Civil Code section 8180, completion occurs on actual completion of the work, on occupation or use by the owner together with a cessation of labor, after labor stops for a continuous 60 days, or when a notice of cessation is recorded after labor stops for a continuous 30 days. Where a public entity must accept the work, completion occurs on acceptance.

Public works run on a different statute with shorter subcontractor timing. As of November 2026, the two line up like this.

Rule Private works (Civil Code) Public works (Public Contract Code)
Retention cap 5% of each payment and of the contract price, contracts on or after Jan. 1, 2026 (8811) 5% of each payment and of the contract price, contracts on or after Jan. 1, 2012 (7201)
Release to the contractor Within 45 days after completion (8812) Within 60 days after completion (7107)
Payment to subcontractors Within 10 days after receipt (8814) Within 7 days after receipt (7107)
Good-faith dispute Up to 150% of the disputed amount may be withheld (8812, 8814) Up to 150% of the disputed amount may be withheld (7107)
Late payment 2% per month, plus costs and attorney’s fees (8818) 2% per month, plus costs and attorney’s fees (7107)

For a subcontractor, the practical gap is the clock. On a public job the original contractor has 7 days to pass retention down. On a private job it has 10. Public Contract Code section 7107 also has separate timing for some state agency contracts, and it says any attempted waiver of its terms is void.

What happens if retention is paid late or disputed?

Under California Civil Code section 8818, an owner or direct contractor that fails to pay retention on time owes a penalty of 2 percent per month on the amount wrongfully withheld, in place of any interest otherwise due. In a lawsuit to collect it, the prevailing party recovers costs and reasonable attorney’s fees.

The penalty reaches only retention “wrongfully” withheld, and a good-faith dispute changes the math. Sections 8812 and 8814 let the owner, or the direct contractor, hold back up to 150 percent of the disputed amount. They do not let anyone sit on the whole retention because one line item is contested.

Retention disputes can look like disputes over the work. Our construction lawyers for contractors page notes that “an owner or general contractor will sometimes raise defect allegations to avoid paying a contract balance.” When that happens, the size of the withholding and the timing of the defect claim both matter.

Unpaid retention is part of the unpaid contract balance. Depending on the project and the facts, the tools for collecting it can include a mechanics lien, a stop payment notice, a payment bond claim or a contract claim. Each has its own notice rules, so check them early. Our guide to how a mechanics lien works in California covers the basics.

Write down the completion date the moment it happens. The 45-day and 10-day clocks run from completion and from receipt, and a penalty claim is much easier to prove when those dates are documented.

How is retention different from a progress payment?

A progress payment is a payment for work performed as the project moves along. California Civil Code section 8800 requires an owner to pay an undisputed progress payment within 30 days after the contractor’s notice demanding payment under the contract, except as otherwise agreed in writing by the owner and direct contractor.

Retention is the slice held back from those progress payments. Section 8800 says it “does not supersede any requirement” of the retention article that begins at section 8810, so the two sets of rules sit side by side. A contractor can be paid on time on every progress bill and still have a retention problem at the end of the job.

The remedies look similar. Progress payments under section 8800 also carry the 150 percent dispute limit, the 2 percent monthly penalty and fee shifting for the prevailing party.

One holdback is outside both. Civil Code section 8822 says the retention article “does not apply to a retention payment withheld by a lender pursuant to a construction loan agreement.” A developer’s loan holdback is governed by the loan documents, not by sections 8810 through 8818.

For a full discussion of slow pay on progress billings, see our post on how to handle payment disputes in construction.

What to check in a retainage clause before signing

A retainage clause in a California construction contract should state the percentage, the release trigger and how disputes are handled, and each term should match the statutes that apply to the contract date and project type.

Start with the percentage. On a private contract signed on or after January 1, 2026, anything above 5 percent of a payment needs to fit one of the section 8811 exceptions. If the bond exception is the reason, the written bond notice has to go out at or before the bid request, not after award.

Check the flow-down. A subcontract that copies an old form can end up holding a higher percentage than the prime contract, which section 8811 does not allow on covered contracts. If the subcontract also ties payment to the owner paying first, see our post on pay-if-paid and pay-when-paid clauses in California.

Look at the release language. A clause that ties release to a lender’s or architect’s sign-off, rather than to completion, may not line up with the 45-day rule in section 8812 and the definition of completion in section 8180.

Read the dispute terms too. The statutes allow withholding of up to 150 percent of a disputed amount. A clause that lets the payer keep all retention over any dispute deserves a second look.

The firm’s construction agreements practice covers payment terms, “whether retainage applies, and what happens if payment is delayed or disputed.”

Frequently asked questions

Does California’s 5% retention cap apply to contracts signed in 2025?

No. Civil Code section 8811 applies only to contracts for a private work of improvement entered into on or after January 1, 2026. A contract signed in 2025 is outside the cap, even if the work continues into 2026. The release deadlines in Civil Code sections 8812 and 8814 are not tied to that date, so the 45-day and 10-day payout rules still matter on older contracts.

Does the 5% cap apply to homes and apartment buildings?

It depends on the building. Civil Code section 8811 excludes residential projects that are not mixed-use and are no more than four stories. Under that wording, a residential building of four stories or fewer with no other use is outside the cap. A mixed-use building, or a residential building taller than four stories, is covered for contracts entered into on or after January 1, 2026.

Does the retention law cover a construction lender’s holdback?

No. Civil Code section 8822 says the retention payment article does not apply to a retention payment withheld by a lender under a construction loan agreement. The release deadlines in sections 8812 and 8814 and the 2 percent monthly penalty in section 8818 apply to owners and contractors. A lender’s holdback follows the loan documents, so read them alongside the construction contract.

Can a public agency withhold more than 5 percent retention?

Sometimes. Public Contract Code section 7201 caps public works retention at 5 percent for contracts entered into on or after January 1, 2012, but allows more on a project found to be “substantially complex” before bidding. State agencies must explain that finding in the bid documents. Local agencies must approve it at a properly noticed public hearing. A separate exception covers subcontractors who fail to furnish a required performance and payment bond.

How we can help

Stryker Slev Law Group reviews construction agreements and subcontracts for owners, developers, general contractors and subcontractors throughout San Diego, Los Angeles and Southern California, including payment terms and whether retainage applies. When retention is held past the statutory deadline, the firm pursues payment through mechanics liens, stop payment notices, payment bond claims and contract claims where the facts support them.

You talk directly with the attorneys handling your matter, partners Dennis Stryker and Monica Slev. The firm’s office is at 1620 Fifth Avenue, Suite 770, San Diego, CA 92101.

To have a retention clause or a withheld payment reviewed, call (866) 531-5705 or contact Stryker Slev Law Group.

This article is general information and is not legal advice. Retention rules turn on when a contract was signed and what it says, so talk with a construction lawyer about your project.

Negotiating Fair Contracts for LA Real Estate ProjectsPrev
Pay-If-Paid vs. Pay-When-Paid Clauses in California SubcontractsNext

Latest Posts

by Admin

Pay-If-Paid vs. Pay-When-Paid Clauses in California Subcontracts

California courts treat pay-if-paid and pay-when-paid clauses very differently. See what Clarke v. Safeco and Crosno v. Travelers mean for subcontractors...

Pay-If-Paid vs. Pay-When-Paid Clauses in California Subcontracts

Construction LawNovember 19, 2026
by Admin

Understanding Retainage in Los Angeles Construction Contracts

California now caps retention at 5 percent on private contracts signed on or after January 1, 2026. See how retainage works on Los Angeles projects, when it...

Understanding Retainage in Los Angeles Construction Contracts

Construction LawNovember 19, 2026
by Admin

Negotiating Fair Contracts for LA Real Estate Projects

Real estate projects often succeed or fail long before construction begins. The contract signed at the beginning of a project can determine how the parties...

Negotiating Fair Contracts for LA Real Estate Projects

Construction LawSeptember 26, 2026
logo

At Stryker Slev Law Group, our lawyers highly focus on commercial real estate, business transaction and litigation law. Doing so allows us to be extremely efficient and effective in serving our clients’ needs.

Practice Areas

  • Real Estate Development & Construction
  • Construction Litigation
  • Commercial Real Estate

Contact

San Diego, CA Office:
1620 Fifth Avenue, Suite 770,
San Diego, CA 92101.

Tel:
(866) 531-5705

Fax:
(619) 342-7775

Accessibility: If you are vision-impaired or have some other impairment covered by the Americans with Disabilities Act or a similar law, and you wish to discuss potential accommodations related to using this website, please contact our Accessibility Manager at (866) 531-5705.

© 2026 Stryker Slev Law Group. Privacy Policy. All Rights Reserved. Powered by Golden Seller Marketing